Siesta Key’s North Bridge is getting some after-hours attention.
Temporary overnight alternating lane closures are expected this month on the Sarasota Bay Drawbridge No. 170061, also known as the North Bridge, on County Road 758/Siesta Drive.
The information was presented to members and guests during the June 4 Siesta Key Association (SKA) meeting, which was led by President Catherine Luckner and acting Treasurer Bob Luckner. The update came from a Florida Department of Transportation RoadWatch report sent by Nancy Morgan of FDOT.
According to the FDOT update, overnight alternating lane closures are expected through July 14, weather permitting. Motorists can expect overnight lane closures from 9 p.m. to 6 a.m. while crews repair the concrete bridge deck and apply an epoxy overlay protection.
“It’ll go on for about a month,” Bob Luckner said June 4.
No lane closures are scheduled during the Fourth of July holiday period. In the update, Morgan said FDOT normally closes down projects on holidays for the convenience of the traveling public and for the safety of FDOT crews. Crews are not scheduled to work weekends on the project, so no lane closures are expected Friday, July 3, through Sunday, July 5.
Bob Luckner attributed the holiday closure to the Siesta Key Chamber of Commerce working with FDOT due to expected holiday traffic.
“Good job!” he said to a representative of the chamber in attendance at the June 4 SKA meeting, as other attendees applauded the action. “You can expect to see flagmen and barrels out here, but I think it will be safe, and by choosing to do it at night, and not on a holiday weekend, I think the traffic is going to be manageable.”
The bridge rehabilitation project includes concrete maintenance, rehabilitation of mechanical and electrical systems, structural steel repairs and steel coating replacement. FDOT said the work is intended to minimize the effects of the aggressive marine environment on the bridge.
“Certainly, protecting the new decking they put on there five years ago with some coating and welding is time well spent,” Luckner said.
Flaggers, barrels and warning signs will be in place during overnight work. Pedestrians and bicyclists will be escorted through the work zone, and pedestrian and bicycle traffic will remain open at all times.
Work underneath the bridge span will continue Monday through Friday from 7 a.m. to 5 p.m. Residents closest to the bridge should anticipate noise and lights from construction equipment, while residents throughout the project limits should expect construction-related noise.
Bridge openings will continue as normal. Project completion is expected in late 2026.
According to information provided by FDOT, the project improvements include concrete crack and chip repair; structural steel repair; mechanical and electrical system maintenance; cathodic protection to prevent corrosion of steel reinforcement within concrete; and bridge openings to test mechanical systems will coincide with normal openings when possible.
Weekly “road watch” updates will be provided through the FDOT website at https://www.swflroads.com/project/451280-1. FDOT can be followed on Facebook at facebook.com/MyFDOTSWFL and on Instagram at instagram.com/myfdot_swfl.