Roundabout formally tossed to curb

Articles you may have missed

Siesta Sand Legacy Articles Archives

A single excessive bid and lack of public interest means the intersection will be enhanced and additional funds reallocated

By ChrisAnn Allen

It’s official, the commission has nixed construction of a roundabout at the intersections of Beach and Midnight Pass roads.

Due to an $8.9 million price tag and lack of public interest, during a July 10 meeting, Sarasota County commissioners unanimously voted to do away with the project, instead using $400,000 – $500,000 of the allocated $2.9 million Florida Department of Transportation funding to enhance safety features at the existing intersection. The topic was brought up for formal consideration following consensus on the matter at a May 15 budget meeting.

Intersection history

Originally, the intersection was part of an FDOT road but was transferred to the county in 2019 in a road transfer agreement. In exchange for making River Road a state road, the county assumed authority for the portion of Stickney Point Road west of the intersection with U.S. 41. The other Siesta segments to be transferred, designated State Road 758, encompass North Midnight Pass Road, part of Higel Avenue and part of Siesta Drive.

However, prior to the swap, FDOT started an “intersection evaluation project” in 2015 at the location of the intersection. They considered three alternatives: no build, signalized intersection improvements or a roundabout. Public input led to the signalized improvement option but would be enhanced with pedestrian improvements. FDOT preferred the roundabout option. Ultimately, as part of the transfer agreement, the county became responsible for the project. Upon revisiting the matter in 2020, a survey of county residents showed the majority of those not living on the Key preferred a roundabout, while the majority of those residing on the Key would prefer “no change.” So, in December 2020, the board chose to proceed with a roundabout, with funding for design approved in January 2021, amended design costs approved in February 2022, and construction and engineering costs approved in March 2023, all unanimous.

The design plans include flashing beacons at crosswalks, 10-feet wide sidewalks around the perimeter, bike ramps between the road and sidewalks, paved shoulders, street lighting and reduced speed around the roundabout. Anderson said July 10 that pedestrian and bicycle safety design features were a priority, as “that’s been one of the major concerns of the public and ourselves as well, to make sure that whatever we do there it does provide safer pathways for the bicycle and pedestrian community, which is significant right adjacent to the county park.”

He said they put the project out to bid earlier this year, with construction estimated at $4.2 million, but the only bid received was $8.9 million. He said the initial bid was “shocking,” however, consulting with FDOT showed the cost was comparable to bids they received for similar projects, and they recommended canceling the bid then rebidding the project in 12-18 months when changes in the economy could result in more competitive bids. In May, the board requested revisiting project options, which includes continuing with the roundabout and proceeding with the current bid or canceling the bid and waiting 12-18 months, or scrapping the project and adding signals or leaving the intersection as-is.

Discussion and decision

“We are back to talk about options, which the board asked for, on what’s the next steps,” Anderson said. “$8.9 million is a lot of money.” He said they could continue with the roundabout project as the state has committed to funding it but reasserted that is a high cost for an intersection project. “It just seems out of order with reality,” he said, adding if they abandon the project, they could request FDOT reallocate some funding to re-signaling the intersection. He said another option brought forward by Siesta Key residents is to resurface the area and update the pedestrian crosswalks while maintaining the intersection as-is, at a cost of $400,000 – $500,000 based on the current contractor for resurfacing on the Key.

“Those of us that live and work on Siesta Key appreciate all your efforts,” District 2 Commissioner Mark Smith said. “But basically 62% of the folks didn’t want the roundabout.” He said the people living there like the intersection as-is with improved paving and crosswalks and recommended the $400,000 – $500,000 option, with the remaining $2.4 million in FDOT funds reallocated to another project. “Wherever we could use it that FDOT is willing to spend it,” he said of the money. “But the will of the folks out there is ‘thank you, but no thank you.’”

District 5 Commissioner Ron Cutsinger agreed with Smith. “It makes a lot of sense to me,” he said. “Especially since it’s pretty clear this isn’t in desperate need or desperately wanted.” Cutsinger then asked Anderson to clarify his statement regarding FDOT’s commitment to “fully funding the project,” and asked if that meant if the county rebid the project in 18 months and received a $6 million bid, would FDOT cover the cost. Anderson said FDOT has allocated $2.9 million and the commitment to fund is verbal without a binding contract. Cutsinger suggested allocating any additional FDOT funds to improvements on South River Road.

District 4 Commissioner Joe Neunder, whose district covers part of the Key, also agreed with Smith. “I think it’s a good way to just pause the project for now,” he said, suggesting another survey might be appropriate at a future date. He also agreed that the unspent FDOT dollars would be best spent on South River Road. District 3 Commissioner Neil Rainford said he supported the statements of the other commissioners, and District 1 Commissioner, Chair Mike Moran asked County Administrator Jonathan Lewis how they should proceed. Lewis asked for a motion bringing back “the necessary steps to make that happen,” regarding the estimated $400,000 – $500,000 in improvements to the intersection of Beach and Midnight Pass roads, with the rest reallocated to South River Road, which was made by Cutsinger and unanimously approved by the board.

“I just want to say there is a sigh of relief on Siesta Key right now,” Smith said preceding the vote. “We appreciate all the county’s assistance in repaving the intersection and are grateful we are able to help South River Road.”