The legal battle over a proposed Siesta Key beachfront development isn’t over yet.

Despite a Sept. 11 ruling dismissing its challenge to Sarasota County’s denial of a coastal setback variance, Saba Sands II LLC is seeking to revive the case, citing a recent appellate decision that its attorneys contend supports reconsideration.

Sarasota County formally opposed the request Oct. 12, asking Circuit Judge Hunter Carroll to uphold the dismissal or, alternatively, consider additional evidence concerning the developer’s decision to terminate earlier dispute resolution proceedings.

The latest filings follow County Attorney Josh Moye’s announcement of the dismissal during the Sept. 22 Sarasota County Commission meeting, when he characterized the decision as a favorable outcome for the county.

“Our office filed a motion to dismiss as untimely filed, and the court ultimately agreed and issued an order dismissing the case,” Moye told commissioners.

He credited Deputy County Attorney David Pearce as lead counsel, assisted by Jennifer Burns, and said no further commission action was necessary.

The dispute stems from the commission’s unanimous Nov. 19, 2024, denial of a coastal setback variance requested by Saba Sands II, whose registered agent is Sarasota attorney William A. Saba.

The company sought permission to construct a three-story, two-unit residential building over ground-level parking on approximately 1.13 acres of beachfront property seaward of Tenacity Lane, near Siesta Key Beach Access 10.

The proposed construction would extend approximately 229 feet seaward of the county’s Gulf Beach Setback Line, established to protect coastal dunes, vegetation and nearby properties from erosion, storm surge and flooding.

As previously reported by Siesta Sand, county officials raised concerns about the project’s potential effects on coastal systems, its consistency with comprehensive plan policies and whether the developer had demonstrated sufficient hardship to justify the variance.

Following the denial, Saba Sands initiated proceedings Jan. 22, 2025, under the Florida Land Use and Environmental Dispute Resolution Act, known as FLUEDRA.

The law provides an alternative dispute resolution process for property owners who believe government land-use decisions unreasonably restrict their property rights.

The parties participated in mediation, which ended Aug. 18, 2025, without an agreement. Saba Sands subsequently filed a petition for a writ of certiorari Sept. 17, requesting judicial review of the county’s denial.

The latest legal dispute centers on how Florida law calculates the deadline for seeking that review. Under state appellate rules, a certiorari petition generally must be filed within 30 days of a final government decision. FLUEDRA suspends that deadline while qualifying dispute resolution proceedings are underway.

In his Sept. 11 order, Carroll determined the filing period began Jan. 15, 2025, when the county’s written denial became final, and stopped seven days later when Saba Sands initiated FLUEDRA proceedings.

He concluded that the clock resumed Aug. 18, when the developer abandoned the dispute resolution process. Because Saba Sands waited another 30 days to file its petition, Carroll found that it exceeded the remaining 23 days available and dismissed the case for lack of jurisdiction.

Attorneys Morgan Bentley and Ashley Gaillard challenged that interpretation in a Sept. 25 motion for rehearing, arguing that FLUEDRA expressly pauses the judicial review deadline until a local government acts on a special magistrate’s recommendation.

Because no recommendation was issued following mediation, the attorneys contend that the filing deadline remained suspended.

“Saba Sands did not concede that it abandoned the FLUEDRA proceeding; it conceded only that the mediation session ended without agreement,” the motion states.

The developer’s filing cites Traska v. Board of County Commissioners of Brevard County, a Sept. 10 decision by Florida’s 5th District Court of Appeal addressing statutory obligations involving an incomplete FLUEDRA proceeding.

Saba Sands argues that the ruling supports reinstating its petition, although the appellate court did not decide the Siesta Key case.

Also on Sept. 25, former Florida Senate President Bill Galvano, of Bradenton-based Grimes Galvano PL, entered a formal appearance as additional counsel for Saba Sands.

Galvano, who served as Senate president from 2018 to 2020, joins the developer’s existing legal representatives from Bentley Goodrich Kison PA.

On Sept. 28, Carroll ordered Sarasota County to respond to the rehearing request by Oct. 13.

The county filed its 51-page response, including exhibits, Oct. 12, arguing that the developer voluntarily terminated the FLUEDRA process and consequently missed the deadline for seeking judicial review.

County attorneys contend that the Traska decision involves materially different circumstances because Saba Sands elected not to proceed beyond mediation to a hearing on the merits of its dispute.

They also submitted correspondence, the special magistrate’s engagement agreement and billing records in support of their position.

According to the county’s filing, special magistrate Ken Tinkler confirmed following the unsuccessful August 2025 mediation that he would not issue a recommendation because Saba Sands had elected to terminate the process.

The developer disputes that characterization, maintaining that ending mediation did not constitute abandonment of the broader FLUEDRA proceeding.

Alternatively, the county requested an evidentiary hearing to determine whether the developer abandoned the process.

County attorneys also argued that if a special magistrate’s recommendation was legally required, the dispute could be considered premature for judicial review.

Should Carroll reach the merits, the county maintains that commissioners followed proper procedures and that their decision was supported by competent, substantial evidence.

The court proceedings follow an unsuccessful settlement effort earlier this year.

In February, commissioners unanimously rejected a proposal under which Saba Sands would reduce the proposed development from two residential units to one and decrease its air-conditioned living space.

Alternatively, the company offered the county an opportunity to purchase the property for $8 million.

Moye recommended rejecting both options, noting that county appraisals valued the property at $3 million and $4 million, while an appraisal submitted by Saba Sands placed its value at $5.5 million.

The coastal setback variance remains denied, and Carroll’s dismissal did not determine whether the proposed development should be permitted.

With both sides having presented their latest arguments, the question now is whether the developer’s challenge can proceed. 